UBC Rover — Last Planner System (LPS) Engine

Mapping Competition Requirements $\rightarrow$ System Architecture $\rightarrow$ 3-Week Lookahead Execution

For UBC Rover Operations & Subteam Leads
Target: University Rover Challenge (URC) 2027 & Canadian International Rover Challenge (CIRC) 2027


🧭 Executive Summary: What is This Project?

Traditional engineering project management tools (Gantt charts, basic Excel trackers, or flat task boards) always break down in student robotics teams. Tasks get assigned before prerequisites exist, leads get blocked by silent upstream delays, and nobody knows why a milestone slipped until it's too late.

This project implements an adapted version of the Last Planner System (LPS)—a lean production management workflow originally developed in Lean Construction—customized specifically for the realities of UBC Rover.

The Problem We Are Solving

  1. The "Critical Web" vs. Linear Gantt Charts: Engineering a Mars rover isn't a straight line. It is an interconnected web where a single physical subsystem (like the Chassis Baseplate) has 10+ subteams and modules feeding into it, and capabilities (like "Stable while drilling") cannot be solved until upstream tools (like the Rover Lab sampling tool) have settled their reaction forces and mounting geometry.
  2. Busy Student Volunteer Bandwidth: Leads should never be handed a blank template or forced to do complex dependency mapping in huge spreadsheets with 120+ competition requirements.
  3. The Go-Ahead Checklist (Go / No-Go Decision):
    • A common mistake in project management is requiring "CAD Frozen" before starting a task, when a huge portion of the team's work is design itself!
    • In our system, the Soundness check is a Go / No-Go Checklist needed to actually start making, purchasing, or committing to execution:
      1. Upstream / Interface Defined: The upstream task is done OR its physical/electrical interface is defined (we know what it connects to / looks like; physical prototypes do not have to be done to take on a downstream task).
      2. Design & Scope Defined: Clear concept, dimensions, and understanding of what we are creating.
      3. Exact Parts & Budget Specified: Bill of materials and exact parts specified for budget approval and purchasing.
      4. Tooling & Equipment Ready: We know which tools, machines, or 3D printers we need first and have confirmed access.
    • When all 4 checks pass, the task is Go-Ahead Ready (Sound for the 3-week rolling lookahead). If any check fails, it is marked No-Go / Blocked, prompting for an explanation and a standardized Reason for Variance (RFV 1–6) code.

🏗️ How the System Connects (The Traceability Chain)

Everything in our rover connects in a closed loop from competition points down to weekly work:

┌────────────────────────────────────────────────────────┐
│             URC 2027 Competition Rules                 │
│      (ASTRO-##, DELIV-##, EQUIP-##, AUTO-##)           │
│        Scored capabilities rated: YES / TOUGH / NO     │
└──────────────────────────┬─────────────────────────────┘
                           │ fulfills
                           ▼
┌────────────────────────────────────────────────────────┐
│            Multi-Level System Architecture             │
│            (draw.io System Block Diagrams)             │
│      Competition -> Rover -> Chassis/Arm/Compute...    │
└──────────────────────────┬─────────────────────────────┘
                           │ implemented by
                           ▼
┌────────────────────────────────────────────────────────┐
│              Subteam Deliverables (TSK-###)            │
│            120 Atomic Subteam Engineering Tasks        │
└──────────────────────────┬─────────────────────────────┘
                           │ screened by
                           ▼
┌────────────────────────────────────────────────────────┐
│          LPS 3-Week Rolling Lookahead & Constraints     │
│   [CAD Frozen?] [Parts Here?] [Tools Ready?] [Handoff?]│
│             Sound -> Committed in Weekly Plan          │
│        Blocked -> Tagged with Variance Code (RFV)      │
└────────────────────────────────────────────────────────┘

🛠️ The 3-Step Agentic Roadmap (Where We Are)

We are executing this rollout in strict phase gates with our AI assistant:

  • STEP 1: Define Setup Plan & Architecture (Completed ✅)
    • Established the relational schema linking Requirements $\rightarrow$ Architecture Nodes $\rightarrow$ Atomic Tasks.
    • Extracted and saved the team context, anchor dates, subteam lead ownerships, and tie-breaker protocols.
  • STEP 2: Bulk Ingestion & Intermediary Triage Micro-App (CURRENT PHASE 🔄)
    • Parsed raw input files (system_architecture.xml, subteam_requirements.xlsx, budget_and_schedule.xlsx, and urc_rules_2027.pdf).
    • Built this disposable local micro-app (app.py) so Andres, Rowan, and the Leads can rapidly link multi-input/output dependencies and screen constraints via UI buttons instead of walls of text chat or fragile spreadsheets.
  • STEP 3: Production Deployment & Critical Web Engine (Next Phase 🚀)
    • Feed the triaged dataset (lps_data.json) back to the AI agent to compute the full Critical Web, generate automated dependency layers, and deploy the final production tracking system (integrated with MS Planner / GitHub or a lightweight cloud dashboard).

🖥️ What is the Step 2 Micro-App?

Rowan: "On first look it looks really busy."
Andres: "It is, this is an intermediary tool... just to define and interlink all of our requirements. I think all the links will be difficult in Excel."

This micro-app is not the final weekly dashboard for the general team. It is a specialized workbench designed for Operations (Andres, Rowan, Noah, Anika, Ben) to sit down and rapidly interlink the messy baseline data.

Key Capabilities of the Micro-App:

  1. Multi-Input & Multi-Output Linking:
    • Architecture Nodes: Select 1 Primary node, and click + Add Node to attach secondary interfacing nodes.
    • Competition Requirements: Attach multiple URC point-scoring capabilities (ASTRO-##, DELIV-##, etc.) to a single task.
    • Upstream Prerequisites: Select which predecessor tasks block this work from starting.
    • Downstream Handoffs: Designate which subteams receive the output when complete.
  2. The Go-Ahead Checklist (Go / No-Go Decision):
    • Before any task is considered "Ready" for the 3-week lookahead, it must pass 4 gates:
      1. 1. Upstream / Interface Defined (Know what it connects to / looks like; physical prototype not required)
      2. 2. Design & Scope Defined (Clear concept & dimensions of what we are creating)
      3. 3. Exact Parts & Budget Specified (BOM & part costs specified for budget & purchasing)
      4. 4. Tooling & Equipment Ready (Know which tools/machines/printers are needed & have them)
  3. Reason for Variance (RFV) Logging:
    • If a task is blocked or misses its commitment, leads tag it with one of the team's standardized variance codes:
      • RFV-1: Upstream Handoff Delay
      • RFV-2: Parts / Machine / Printer Bottleneck
      • RFV-3: Scope / Integration Surprise
      • RFV-4: Academic Crunch (Midterms/Finals)
      • RFV-5: Overcommitment / Bandwidth Exceeded
      • RFV-6: Funding / Budget Hold
  4. Tie-Breaker Rule:
    • Noah (Systems Lead) breaks cross-subteam integration and dependency ties, with final sign-off by Captains Andres & Rowan.

🚀 Running the Micro-App Locally

The micro-app is completely self-contained in a single lightweight Python script with an embedded UI. No complex web servers or Node.js required.

Prerequisites

  • Python 3.8+ installed on your machine.

Quick Start

  1. Open your terminal in this repository folder:
    # 1. Install Flask (one-time)
    pip install -r requirements.txt
  2. Start the micro-app:
    # 2. Run the server
    python app.py
  3. The app will automatically open your browser to:
    http://localhost:5000
    
  4. Click through your subteam tab, link prerequisites/nodes, toggle constraints, and click Save Changes.
  5. All updates write directly to lps_data.json. Commit and push your changes to GitHub!

📁 Repository Structure

ubc-rover-lps/
├── app.py                   # The Step 2 Flask triage micro-app & embedded UI
├── lps_data.json            # Master working dataset (Tasks, Nodes, Reqs, Constraints)
├── requirements.txt         # Dependencies ('flask')
├── README.md                # This document
│
├── raw_inputs/              # Source of truth raw files from the team
│   ├── system_architecture.xml    # 10-page draw.io system block diagram export
│   ├── subteam_requirements.xlsx  # Anika's URC capabilities sheet (Yes/Tough/No)
│   ├── budget_and_schedule.xlsx   # PATH funding budget & legacy preliminary schedule
│   ├── urc_rules_2027.pdf         # Official URC 2027 competition rulebook
│   └── brain_dump_2026-11-15.md   # Andres's raw operations context & lead notes
│
├── parsed_data/             # Parsed intermediate JSON exports from AI extraction
│   ├── architecture_raw.json      # 86 nodes, 106 edges, 10 pages
│   ├── requirements_raw.json      # 109 scored requirements, 90 overview tasks
│   ├── budget_schedule_raw.json   # 137 budget items, 90 schedule items
│   └── urc_rules_raw.json         # 4 missions, 17 general rules, 9 key dates
│
└── GEMINI.md                # Agent constitution & strict phase-gate protocol

🏷️ Nomenclature & ID Conventions

  • TSK-### — Atomic Subteam Engineering Deliverables (e.g. TSK-012: [Equipment Servicing] arm reach covers ground to 1.5m).
  • ASTRO-## / DELIV-## / EQUIP-## / AUTO-## — Specific URC Competition scoring rules from the official rulebook.
  • Architecture Nodes — Blocks from the draw.io system diagram (e.g. Rover, Chassis, PTZ, Compute, Death Ray).
  • Subteams:
    • ARM: Arm & End Effector (Leads: Will, Matt)
    • CHAS: Chassis (Lead: Eugene)
    • ELEC: Electrical (Official Lead: Darwyn; Acting Lead: Rowan)
    • RLAB: Rover Lab (Lead: Jennifer)
    • SCI: Science (Lead: Jennifer)
    • SW: Software (Leads: Riddhima, Ben, Rowan)
    • OPS: Operations (Andres, Rowan, Anika, Noah, Ben)
    • BIZ: Business (Lead: Angelica)

🎯 The End Goal: How We Will Run Leads Meetings

Once Step 2 triage is complete, the AI agent will compile the linked data into our Step 3 Production System.

In our weekly leads meetings:

  1. No Finger-Pointing: If a task was missed, we don't argue—we log its RFV Code so Operations can kill the root bottleneck (e.g. order more 3D printer filament, adjust for midterm schedules, or fix cross-team handoffs).
  2. Rolling 3-Week Commitment: Each subteam lead commits only to tasks in the 3-week lookahead that are 100% constraint-free (sound).
  3. Visible Critical Web: When a task on the critical path is checked off, its dependent branches automatically unlock across the rover, giving everyone total clarity on what needs to be built next.

About

UBC Rover development of project management tools - currently Last Planner System

Resources

Stars

0 stars

Watchers

0 watching

Forks

Releases

Packages

Contributors

Languages